Farhatabad TPP likely to be revivedIllustrative image – not actual.

The Union government has recommeded for the allotment of coal block for the 1,320 MW Super Critical Thermal Power Plant (TPP) in Farhatabad, Karnataka, which had remained a major hurdle in the establishment of the plant on design, build, finance, operate and transfer (DBFOT) mode.

The Karnataka government has decided to double the power production capacity of the proposed TPP to 2,640 MW instead of the proposed 1,320 MW with the existing land, and has expressed its willingness to increase the marginal additional land and water required for the increased capacity of the power plant.

In early 2011-12, the state government had completed all formalities of acquiring 1,601 acre of land in and around Farhatabad by incurring an expenditure of Rs 158 crore. However, the project got stalled due to the non-allocation of the coal block.

The State government had originally sought a coal linkage of 6.3 mtpa for the 1,320 MW power station.