On 30 May 2023, the Brihanmumbai Municipal Corporation (BMC) completed boring and excavation work for the second and final underground tunnel, which is part of the Mumbai Coastal Road Project (MCRP).
The 10.58 km MCRP is being built to reduce traffic congestion in Mumbai. The high-speed corridor will connect the Marine Drive to the Bandra Worli Sea Link (BWSL) through a series of arterial highways, underground tunnels, and vehicular interchanges.
The twin tunnel will pass under the Arabian Sea, which will be India’s first undersea tunnel. Later, the project will expand to the coastal road towards the suburbs, till Dahisar, Mira Road and Bhayander.
The initial target to complete the project is November 2023. The corridor is expected to be partially opened by this time, and by May 2024, the complete road will be open to the public.