Excavation work begins for NPCIL's Rajasthan unitsIllustrative image – not actual.

The ground breaking ceremony for NPCIL's Rajasthan Atomic Power Project was held on 19 August 2010.

The excavation work commenced for Units VII and VIII of the project having the capacity of 700 MWe each. The cost of constructing the two units is estimated at Rs 12,320 crore. The reactors are scheduled to begin commercial operation in June and December 2016, respectively.

HCC has been awarded a contract by NPCIL to undertake main plant civil works for the units.

Meanwhile, the excavation work has been completed for the two 700 MWe pressurised heavy water reactors at Kakrapar in Gujarat and the company is awaiting approval from the Atomic Energy Regulatory Board to begin pouring concrete.

Related Links:
Project profile