Illustrative image – not actual.Eveready Industries' greenfield dry cell manufacturing unit in Uttaranchal is scheduled to commission by end-2006. Speaking to ProjectsToday, company officials indicated that 90 per cent work on the Rs.75 crore project is complete and full commissioning is expected by December 2006.
The project, coming up in Hardwar district, will produce 400 million pieces of AA-sized dry cells per year.
This is the second large greenfield project of Eveready Industries in recent years. In around 2002, Eveready set up a greenfield unit at Noida for the manufacture of dry cells. For Eveready, this would be the second facility in Uttaranchal, the first being a packaging unit (not manufacturing) at Selaqui Industrial Area in Dehra Dun district.
Eveready officials further indicated that in the near future there are no plans to launch further greenfield projects. Capacity expansion will be carried out through modernisation and expansion of existing facilities.