Illustrative image – not actual.Essar Power is planning to convert two of its gas-based power plants in India into coal-based projects due to an increase in gas shortage.
Essar proposes to replace the gas turbines at the 515 MW Haziara and the 500 MW Bhander plants with equipment that can be fired by burning coal. The entire process will take three years, and upon conversion, the combined capacity of the two units will be reduced to 430 MW. The gas turbines will then be shifted to Nigeria where they will fuel a 330 MW power plant. The power plant in Nigeria is estimated to cost Rs 1,000 crore.
The company has designed the conversion plant in such a manner that the units will run on low-grade imported coal that is abundantly available at economic rates. It has access to approximately 500 million tonne of coal resources across seven coal blocks in India and overseas.
Meanwhile, the company is planning to increase its overall capacity from 3,910 MW to 6,700 MW by 2016.