Essar Steel begins shipping iron ore pellet from Paradip plantIllustrative image – not actual.

Essar Steel has commenced shipping iron ore pellet from its recently commissioned pellet plant at Paradip in Orissa.

The company has sent 40,000 tonne of iron ore pellet to be used at its Hazira steel complex, in Gujarat. In May 2012, it had shipped a small quantity of 5,000 tonne pellet, said a shipping agent based at Paradip. Currently, the pellet plant is in testing phase and will soon start production in full swing once raw material availability is ensured. As per the original plan, the pellet plant will use low grade iron ore fines that will be pumped through pipelines as concentrates from Dabuna in north Orissa to Paradip. The company has finished laying pipelines in about 236 km, but had to halt the work for not getting forest land approval for a 5 km stretch. 