Illustrative image – not actual.The construction of Essar Oil's 10.5 million tonne per annum refinery at Vadinar in Gujarat, is expected to move forward, with Larsen & Toubro providing guarantee to undertake the refinery's physical completion.
According to Mr Jagdeesh Mehta, Managing Director & Chief Executive Officer of Essar Oil, L&T has already undertaken detailed due diligence and has guaranteed to provide an additional Rs.100 crore for physical completion of the project, if required.
ABB, which would supply 90-95 per cent of the refinery equipment, has estimated that the construction would incur an expenditure of Rs.1,145 crore. On the other hand, L&T, following its due diligence, has estimated the cost for completion of the refinery’s physical construction, at Rs.1,250 crore. If ABB is unable to finish construction work within its estimated cost, L&T would finance the construction upto the tune of Rs.100 crore.
ABB has already agreed to bring in a maximum of Rs.905 crore as part of a completion guarantee. The L&T guarantee would ensure project completion. According to Mr Mehta, the stipulated norms specify that a foreign company cannot do physical completion of the refinery, which is why L&T has been roped in.
ABB would also bring in an additional Rs.400 crore as quasi-equity in the total equity of Rs.2,148 crore of the project. The Ruias of the Essar group have contributed Rs.211 crore through internal accruals, while Rs.100 crore has been borrowed from Essar Oil’s energy division.
Once financial institutions disburse the loan component, project construction would commence. The commissioning of the first unit is expected to take 18 months, while the entire project would be completed within 24 months. Actual construction at the site may take 3-6 months to commence.
Related news:
IDBI gives conditional go-ahead to resume Vadinar project