Illustrative image – not actual.Essar Oil is in the process of raising a fresh debt of up to $5 billion (approx Rs.20,000 crore) through ECB and rupee loans to part finance its $6 billion (approx Rs.24,000 crore) Vadinar refinery expansion project in Jamnagar district and has already received in-principle commitment from lenders to the extent of $4.3 billion(approx Rs.17,200 crore).
The capital infusion by the promoters will be to the extent of $2 billion (approx Rs.8,000 crore) in two tranches for the expansion project. The first tranche (of capital infusion by the promoters) of $1 billion (approx Rs.4,000 crore)will be made as soon as the financial closure is completed and the second tranche of $1 billion will be completed by the end 2008.
The company will ramp up the capacity of its refinery from the present 10.5 million tpa to 34 million tpa by 2010.
Also See:
Essar Group plans petrochemical project at Vadinar (14-Apr-08)
Related Links:
Project profile