Essar Oil has reportedly decided to scale up capacity of its upcoming petroleum refinery at Vadinar in Jamnagar district of Gujarat. Capacity would be increased to 16 million tpa from the previously-planned 12 million tpa. The original capacity was intended to be 10.5 million tpa.

Construction work on the refinery project is in full swing, and the refinery is scheduled to commission by April 2006, although it would not operate at full capacity then. It may be mentioned here that earlier in March 2005, Essar Oil had indicated that the refinery would be commissioned by June 2006. (See Related News)

For the first six months on commissioning, the refinery would operate at 3 million tpa (60,000 bpd). Towards the end of 2006, full capacity of 16 million tpa (320,000 bpd) would be attained.

By mid-2006, Essar Oil expects to have 1,500 retail petrol outlets.