Illustrative image – not actual.The main promoters of the Vadinar Refinery -- Essar Oil and its associates -- have committed to bring the entire equity of Rs.1,300 crore required for completion of the long-delayed project.
According to a statement issued by Essar Oil, the plan to complete the 12 million tpa (originally envisaged, 10.5 million tpa) over the next 18-24 months will be honoured.
ABB will continue to be involved with the refinery construction, and Essar Oil might bring in other companies to supplement or complement ABB's involvement in the project.
The project cost is estimated at Rs.9,863 crore, of which Rs.8,563 crore represents the debt component. Having received formal sanction of the lenders for the remaining debt, Essar Oil has now tied up the entire debt component.