Illustrative image – not actual.Essar Oil has decided to delay its Phase II expansion at Vadinar refinery in Gujarat by a year due to sluggish market conditions.
Sluggish market conditions have reportedly forced Essar Oil to postpone the completion of its phase II of capacity expansion by one year to December 2011. As per the original schedule the entire expansion from 10.5 million tpa to 34 million tpa was to be completed by December 2010.
However, the company is confident of completing its first phase of expansion from 10.5 million tpa to 16 million tpa as per schedule. According to the Managing Director, Mr. Naresh Nayyar, the company has already firmed up financing for this project and with the current decision to delay the phase II would modify the funding plan accordingly.