Illustrative image – not actual.Essar Oil has commissioned its optimisation project at its Vadinar refinery in Gujarat.
The project has come up with an investment of Rs 1, 700 crore. The company has completed its optimisation project, which has taken the capacity of its Vadinar Refinery to 20 million tpa or 4,05,000 bpd. The optimisation project has been completed four months ahead of schedule. Essar Oil, 29 March 2012, completed the refinery expansion project to raise its capacity from the current 10.5 million tpa to 18 million tpa on with an investment of Rs 9,100 crore taking the total investment at Vadinar Refinery to Rs 24,000 crore.