Illustrative image – not actual.Essar Oil, on 8 December 2011, commissioned a new isomerization (ISOM) unit at its Vadinar refinery in Gujarat.
The 0.7 million tpa ISOM Unit will help the company produce Euro IV grade petrol of high octane rating and almost zero sulphur content. The unit is a key component of the Phase I expansion of the company's Vadinar refinery that will increase its capacity to 18 million tonne. So far, mechanical completion has been achieved for 27 new units and utilities that are being added as part of the expansion. Mechanical completion of the pending units —- namely the DCU (Delayed Coker Unit), VGO-HT (Vacuum Gas Oil Hydrotreater) and a new SRU (Sulphur Recovery Unit) —- is expected to be completed by end-December 2011.