Illustrative image – not actual.Enron Broadband Services (EBS) has reportedly pulled out of its proposed joint venture (JV) with Maharashtra State Electricity Board (MSEB) and Global Tele-Systems (GTL) for an optic fibre cable (OFC) network project along MSEB’s transmission lines in Maharashtra.
Enron has concluded that its
involvement in the project would not be financially viable because of delays
and disagreements on critical commercial and regulatory issues, between the parties
concerned. According to Enron, it was unclear whether under its charter, MSEB could
allow private operators to lay an OFC network along its transmission lines.
In April 2000, MSEB had selected the
EBS-GTL consortium through the competitive bidding route, for partnering MSEB in
the project. MSEB had sold part of its right of way in the transmission network,
to the consortium, for Rs.101 crore. MSEB was to utilise this amount for
part-funding its stake in the project.
EBS and MSEB were to pick up 40 per
cent stake each in Powertel, the JV company, while GTL was to take the
remaining 20 per cent stake. The Rs.400 crore project entailed laying 5,000 km of
OFC in the State.