Enron
has invoked Central guarantee, for the second time, in a bid to recover dues
payable to Dabhol Power Company (DPC) by Maharashtra State Electricity Board
(MSEB).
MSEB owes Rs.102 crore to DPC towards
payment of power lifted during December 2000. The original deadline for making
the payment was 26 February 2001, but Enron offered a 15-day extension
stretching the payment due date to 10 March 2001.
It may be recalled that sovereign
guarantee was invoked by Enron, for the first time, on 6 February 2001. This
pertained to non-payment of November 2000 dues. These dues were subsequently
settled on 17 February 2001.
Meanwhile, DPC has presented its
February 2001 bill of Rs.113 crore to MSEB.
As of date, the total outstanding dues
payable by MSEB is Rs.342 crore, which includes the bills for December 2000
(Rs.102 crore), January 2001 (Rs.127 crore) and February 2001 (Rs.113 crore).