Electrosteel Castings ferro alloy unit re-scheduled for 2019Illustrative image – not actual.
Electrosteel Castings has commenced execution work on its ferro alloy plant. Currently, work is underway on the unit for setting up of 1x6 MVA and 1x9 MVA submerged arc furnaces for production of silica manganese with a capacity of 14,850 tpa at Haldia in Midnapore district of West Bengal.

The project, spread over 3.19 acre of land, will include five MW waste heat recovery based power unit. The company also intends to produce 6,600 tpa silica manganese for captive consumption at later stage.

In 2016, terms of reference (ToR) was accorded and a year later in April 2017, environment clearance (EC) was granted for the project. Work commenced on the project in 2018 and around 20 percent project work was completed till date, as per the information shared with Projects Today. The promoter also shared that the commissioning of the plant has been re-scheduled to March 2019 instead of February 2019.

Contractor and consultancy services are offered by RgCon Services. Envirotech East is the Environmental Impact Assessment (EIA) consultant. Avant Garde Engineers & Consultants is consultant in-charge for power plant.

← All latest storiesBack to top →