Illustrative image – not actual.Elango Industries is planning to set up an 80 MW coal based group captive power plant at Gummidipoondi near Chennai. The plant is estimated to cost Rs.415 crore, of which the equity component is likely tocost about Rs.125 crore and the balance will come through debt.
It is learnt that, some of the equity holders in Kaveri Gas Power are interested in picking up stake in the proposed 80 MW coal based project. Elango Industries is also in talks with other interested companies.
Elango Industries had tied up with Coal & Oil Co, Dubai which will supply Indonesian coal to the plant and is also trying to get domestic coal allocated for the plant. Equipment suppliers such as BHEL, Thermax, Cethar Vessels and four Chinese equipment suppliers including Dongfang were among those that had submitted bids for supplying boiler, turbine and generator for the plant.
The company will achieve financial closure for the project by December 2008.