Illustrative image – not actual.National Aluminium Co has appointed Engineers India Ltd as contractors for undertaking engineering, procurement, construction supervision and project management for Nalco's Phase II expansion project. Bids for the same were invited in December 2004.
It may be mentioned that EIL is already rendering project consultancy since its appointment in early 2004.
The project costing over Rs.4,000 crore envisages the following enhancement in capacity:
| Facility | Unit |
Capacity Expansion |
||
| By | From | To | ||
| Bauxite Mining | million tpa | 1.5 | 4.8 | 6.3 |
| Alumina Refining | lakh tpa | 5.25 | 15.75 | 21.00 |
| Aluminium Smelting | lakh tpa | 1.15 | 3.45 | 4.60 |
| Captive Power | MW | 240 | 960 | 1,200 |