Eighty-five percent work finished on Guwahati water supply schemeIllustrative image – not actual.
The Assam Urban Infrastructure Investment Program is implementing water supply scheme of 23.79 km for South-East Guwahati in Kamrup district of Assam on DBO basis. The project worth Rs 141.81 crore also comprises a sewage treatment plant with a capacity of 98 MLD.

In July 2016, Shivam Transcon bagged an order worth Rs 37.04 crore for construction of storage reservoirs of various capacities at three locations, approach road and allied works for the project.

In November 2016, Tirupati Cement Product bagged an order worth Rs 79.91 crore for construction of water supply transmission main pipelines and allied works for the project.

As per the latest information available with Projects Today, around 85 percent work on the project has been completed. The completion has been rescheduled for December 2019.