Illustrative image – not actual.The construction cost of the 23.6 km long Metro-2B estimated by MMRDA is around Rs 1,900 crore.
The eight companies that have submitted their financial and technical bids for the Rs 900 crore Phase-I of Metro-2B include J Kumar Infrastructure, Larsen & Toubro, Simplex, IL & FS, CHEC-Tata Project (joint venture), SEL-SPSCPL Joint Venture (Sadhbhav), Afcons Infrastructure, and JMC Projects.
MMRDA is also in the process of purchasing rolling stocks (coaches) for the Metro-2B, Dahisar East – Andheri East Metro-7, and Dahisar-DN Nagar Metro-2A corridor.
Earlier, MMRDA had tendered the whole corridor between DN Nagar and Mandale but later scrapped the bids and divided the project into two phases as the bidders had quoted more than the estimated price.
The bidders shortlisted by MMRDA had quoted Rs 2,293 crore for civil construction on four packages of the alignment between DN Nagar and Mandale. However, the bids were later scrapped.
