Eight coal projects face cost overrunsIllustrative image – not actual.

Eight coal projects undertaken by various Government companies have faced cost overruns due to delay in securing equipment. While the original cost of these eight projects was Rs.4408 crore the revised cost stood at Rs.5863 crore, resulting in a cost overrun of Rs.1455 crore. The delay in commissioning these projects ranges from two years to about eight years.

 

Details of some of the projects that have faced cost overrun are given below:

 

Project

Promoter Company

Original Cost (Rs. Crore)

Revised Cost (Rs. Crore)

Old Completion Date

New Completion Date

Coal Mining Parej East OC Project

Central Coalfields

116

162

March 1999

May 2001

Mine Expansion Project

Neyveli Lignite Corporation

1336

1652

March 1997

March 2003

Coal Mining Dudhichua OC Project

Northern Coalfields

868

1271

March 1998

March 2004

Madhuband Washery Project

Bharat Coking Coal

72

194

 

March 2001*

Coal Mining Jhanjra UG Project

Eastern Coalfields

184

403

March 1994

March 2002

Neyveli Mine - I A Project

Neyveli Lignite Corporation

1032

1107

 

July 2001

Coal Mining Kottadih OC/UG Project

Eastern Coalfields

267

494

March 1998

March 2003

Coal Mining Dipka OC Project

South Eastern Coalfields

533

580

 

May 2001

* The project was expected to be commissioned by this date.