Illustrative image – not actual.Eight coal projects undertaken by various Government companies have faced cost overruns due to delay in securing equipment. While the original cost of these eight projects was Rs.4408 crore the revised cost stood at Rs.5863 crore, resulting in a cost overrun of Rs.1455 crore. The delay in commissioning these projects ranges from two years to about eight years.
Details of some of the projects that have
faced cost overrun are given below:
|
Project |
Promoter Company |
Original Cost (Rs. Crore) |
Revised Cost (Rs. Crore) |
Old Completion Date |
New Completion Date |
|
Coal
Mining Parej East OC Project |
Central
Coalfields |
116 |
162 |
March
1999 |
May 2001 |
|
Mine
Expansion Project |
Neyveli
Lignite Corporation |
1336 |
1652 |
March
1997 |
March 2003 |
|
Coal
Mining Dudhichua OC Project |
Northern
Coalfields |
868 |
1271 |
March
1998 |
March
2004 |
|
Madhuband
Washery Project |
Bharat
Coking Coal |
72 |
194 |
|
March
2001* |
|
Coal
Mining Jhanjra UG Project |
Eastern
Coalfields |
184 |
403 |
March
1994 |
March
2002 |
|
Neyveli
Mine - I A Project |
Neyveli
Lignite Corporation |
1032 |
1107 |
|
July 2001 |
|
Coal
Mining Kottadih OC/UG Project |
Eastern
Coalfields |
267 |
494 |
March
1998 |
March
2003 |
|
Coal
Mining Dipka OC Project |
South Eastern
Coalfields |
533 |
580 |
|
May 2001 |
* The
project was expected to be commissioned by this date.