EID-Parry soon to operationalise port-based sugar refineryIllustrative image – not actual.

EID-Parry, through its subsidiary, Silkroad Sugar, is likely to commence operations at its sugar refinery, a port-based SEZ in Kakinada, Andhra Pradesh, by the end of May 2014.


The project, with six lakh tpa capacity, will initially operate at about four lakh tonne and reach full capacity in 2015-16. It entails an investment of Rs 600 crore. The refinery project was unveiled in 2006 as a JV with Cargill Asia Pacific.

 
The project commissioning was delayed due to lack of adequate natural gas supplies to operate the power plant. The refinery, which was operated for about a year in 2010 and 2011, was then shut down. EID-Parry has recently set up a 10 MW coal-based plant to power the unit.


Further, the company is planning to augment the capacity of the project to 10 lakh tonne in FY17, with an additional investment of about Rs 100 crore.


The SEZ refinery will use imported raw sugar, including imports from EID-Parry’s own mills, to refine and export white sugar.