ECS approves Cairn India's pipeline projectIllustrative image – not actual.

On 25 February 2008, Empowered Committee of Secretaries (ECS) approved Cairn India's proposal to lay a $800 million pipeline which will carry oil from its Rajasthan fields. Cairn had also suggested recovering its cost through sale of crude.

Cairn and its 30 per cent partner ONGC will together lay a 585 km pipeline up to the new sale point. The cost of laying the line will be included in the field development cost. The crude oil delivery point will be from the field flange in Barmer, Rajasthan to Salaya in Gujarat. ESC will not charge Cairn-ONGC a tariff to transport crude, once costs are recovered by the operator and the pipeline is owned by the government.