Godavari Biorefineries has received environmental clearance from the Ministry of Environment, Forest & Climate Change (MoEF&CC) for expansion of its distillery unit in Karnataka.
The project involves expansion of distillery unit from 320 klpd to 400 klpd and ethanol from 293.5 kld to 380 kld located at Saidapur, Handigund, Madbhavi, Sameerwadi, Mudhol tehsil in Bagalkot district.
The existing land area is 4,84,000 sq mtr (48.4 ha) and no additional land will be required for proposed expansion. The investment will be Rs 133.2 crore.
The total employment required will be 150 persons directly and 30 persons indirect after expansion.
The total existing fresh water requirement is 819 cu mtr per day and the existing power requirement will be 5.5 MVV proposed to be met from captive generation.