Illustrative image – not actual.The company is planning to expand cement capacity from 8.8 million tpa to 13.2 million tpa at Ras village, Jaitaran Tehsil in Pali district of Rajasthan.
The company has already received EC for increase of clinker capacity from 11.2 to 15 million tpa, cement from 8.8 million tpa to 13.2 million tpa, waste-based recovery plant from 68 MW to 90 MW, CPP at 180 MW, synthetic gypsum capacity of 1,560 tpd, DG sets capacity of 2,000 kVA.
The project will not require any additional land and the existing area of 187.56 ha is adequate.
The cost of the proposal is Rs 384.68 crore which includes Rs 150 crore for roller press, feeding hoppers, cement silos and packers. Rs 93.18 crore will be utilised for kiln modification of Unit-III to X and Rs 141.50 crore for expansion of waste-based recovery plant.