EC accorded for expansion of Konar open cast coal mineIllustrative image – not actual.

The Ministry of Environment, Forest and Climate Change (MoEF&CC) has accorded environmental clearance for the expansion of Konar opencast coal mine.

The project by Central Coalfields involves expansion of Konar OCP from 4.10 million tpa (Normative) / five million tpa (Peak) to eight million tpa (Normative) / 11 million tpa (Peak) along with non-coking coal washery of seven million tpa on build-own-operate (BOO) basis, in the total area of 471.40 ha, situated in Bokaro and Kargali area, in Bokaro district of Jharkhand.

The total cost of the project is Rs 1,286.54 crore for OCP and Rs 251.48 crore for washery.

The total project area will be increased from 520.93 ha to 547.38 ha. The total geological reserve is 146.74 million tonne. The mineable reserve is 115.65 million tonne.

The total project life (of the mine is 14 years + washery is three years) including three years washery development period.