Illustrative image – not actual.The Rs 950-crore Eastern Freeway corridor project is on track and is likely to complete in the next two years.
The 22-km-corridor is to be executed in three phases: the first phase 12-km-stretch from Fort to Anik depot that includes P DMello Road; the second phase 5-km-stretch from Anik to Panjarpol (Shivaji Square); and Panjarpol to Mankhurd and then to Ghatkopar on the Eastern Express Highway.
Phase I is likely to span 12 km and entail a cost of Rs 531 crore. A part of this road will be elevated along P DMello and Port Roads. The phase comprises widening and beautification of P DMello Road, flyover at Carnac Bunder and elevated road between Carnac Bunder and Wadi Bunder. Currently, around 40 per cent work is completed and the completion is slated for July 2011.
Phase II, a six-lane road with a flyover, two 500 mtrs tunnels and four bridges total 5 km in length. This phase is to cost Rs 221 crore. Around 30 per cent of the construction work on the road and tunnel has been completed with final completion is expected in June 2011.
Phase III costing Rs 196 crore is to span over 4.5 km envisages a 20 mtrs elevated road above the metro rail at Shivaji Square, which also have an elevated four-lane road of 2.5 km.