East-West metro corridor project continues to face hurdlesIllustrative image – not actual.

Confusion over stake holding and lack of decision making are major impediments in implementing the East-West metro corridor project in Kolkata.

 

Originally promoted by the West Bengal government and the Union Urban Development Ministry, through a 50:50 venture, the project is now held by Indian Railways and the Urban Development Ministry.

 

Later, the Railway Ministry proposed to take complete control of the project. Responding to its request, the Urban Development Ministry also agreed to offload its remaining 24 per cent stake to the Railways.

 

As per Japan International Cooperation Agency (JICA) - the lender to the project - confusion over offloading the Urban Development Ministry's stake to the Railways, impacted decision making on the project.

 

Among other issues that are affecting the project's implementation is the West Bengal government's proposal for route alignment to avoid acquisition of approximately 0.5 acre of land in central Kolkata.

 