East Delhi Municipal Corpn gets nod to raise capacity of C&D waste plantIllustrative image – not actual.
The East Delhi Municipal Corporation (EDMC) has received permission from the Delhi Pollution Control Committee to increase the capacity of its plant in Shastri Park. The move will speed up the process of recycling construction and demolition (C&D) waste. 
 
The plant, inaugurated in 2016, can now daily process and recycle up to 1,000 tonne of waste in comparison to 500 tonne earlier. 
 
Though EDMC has started dumping 700 tonne C&D waste at the plant every day, it is waiting for a concessionaire operating the plant to augment its capacity. 
 
The permission for the capacity expansion was granted in March 2020; however, the process got delayed due to COVID-19 and some financial issues within the company. 
 
The company is expected to start making byproducts in large quantities from December 2020. 
 
Since 2016, the company has claimed to dump at least eight lakh tonne waste, collected from 54 spots, at its 2.5 acre plant. Of this, at least 1.7 lakh tonne was recycled to make byproducts and were supplied to construction sites of various government departments. The remaining was also processed and utilised for other purposes. 
 
About one lakh tonne C&D waste is now lying at the plant and the company expects to clear all waste in one year after augmenting the capacity.

 