EAC soon to consider projects of NMDC Illustrative image – not actual.

The Expert Appraisal Committee (EAC) for non-coal mining, an advisory body in the Ministry of Environment & Forests (MoEF), is likely to soon consider two stalled projects of NMDC for grant of terms of reference (ToR).

 

Both the projects are in Chhattisgarh. These are: the iron ore pelletisation plant at Bacheli; and construction of a 150 km long slurry pipeline from Bacheli to the company's Nagarnar steel project.

 

The iron ore pelletisation plant of the company is estimated to have four million tpa capacity and will entail an investment of Rs 787 crore.

 

Due to delay in getting clearance, construction of the slurry pipeline and the beneficiation plant will not impact the steel plant initially, but the cost will rise if these two projects get prolonged.

 

Besides, construction of the 32 km long water pipeline, which is also part of the Nagarnar steel plant, is among the stalled projects of NMDC. The pipeline corridor requires forest clearance as it falls in forest area of 27.50 hectares.

 

At Nagarnar, in Bastar district of Chhattisgarh, NMDC is developing a three million tpa steel plant, which entails an investment of Rs 15,525 crore.