Illustrative image – not actual.Reliance Industries has secured backing of the key expert appraisal committee in the Ministry of Environment, Forest and Climate Change (MoEF&CC) for expansion of Jamnagar refinery. The company intends to expand the capacity of its export-oriented refinery in the special economic zone (SEZ) at Jamnagar by 5.8 million tonne.
The planned expansion will raise the installed capacity of the SEZ refinery to 41 million tonne from 35.2 million tonne and lift the overall capacity of the Jamnagar refinery complex to 74 million tonne.
Reliance Petroleum, a unit of Reliance Industries, built its first refinery at Jamnagar with an installed capacity of 18 million tonne which was later expanded to 27 million tonne.
However, the EAC, after deliberations and in terms of the provisions contained in para 7(ii) of the EIA Notification, 2006, exempted the project from fresh EIA studies and public hearing, and recommended the project for grant of environmental clearance for a period of one year, with the terms and conditions already stipulated in the existing environmental clearance dated 30 March 2010 granted in favour of Reliance Jamnagar Infrastructure
The capacity of the Jamnagar refinery and petrochemical complex was further expanded by Reliance Industries to 59.7 million tonne during which the production was split between Reliance Petroleum (26.7 million tonne) as an only for exports refinery unit and Reliance Industries (33 million tonne) that sold most of its products in the local market.
The capacity of the SEZ refinery was further expanded by Reliance Jamnagar Infrastructure to 35.2 million tonne from 26.7 million tonne.