The Expert Appraisal Committee (EAC) has given approval to power projects with total proposed capacity of 5,674 MW.
The EAC has cleared the projects in two successive meetings held on 7-8 March and on 14-15March 2011.
They are
| Company | Project |
| DMIC Development Corporation | 1,300 MW plant in Raigarh, Chhattisgarh |
| DMIC Development Corporation | 1,300 MW plant at Guna, Madhya Pradesh |
| Adani Power | 1,320 MW plant in Rajasthan |
| Adani Power | 270 MW unit in Jharkhand |
| Adani Power | 12 MW biomass project in Chattishgarh |
| Indiabulls | 1,350 MW plant in Amravati, Maharashtra. |
| ARS Metals | 120 MW captive power plant in Tamil Nadu |
| Raymond | 7.2 MW captive power plant in Gujarat |