Illustrative image – not actual.Damodar Valley Corporation (DVC) is planning to add about 1,500 MW thermal power capacity.
One unit of 500 MW each at the greenfield power plants at Durgapur in West Bengal and Koderma in Jharkhand are to be operational by March 2011. On completion, both the plants are expected to generate 1,000 MW (2x500 MW) each. The plants are scheduled to be fully operational by December 2012.
Unit I of 500 MW at Koderma thermal power station (TPS) has already been put in trial generation mode. A unit of similar capacity is to be commissioned at Durgapur Steel TPS shortly.
The Unit VII of 500 MW under the Phase II of the Mejia TPS in Bankura district of West Bengal is expected to be fully operational by February 2011.