Illustrative image – not actual.Damodar Valley Corporation has planned to invest Rs.18,000 crore to add 4,500 MW of fresh power capacity by 2012. The expansion plan will be financed through internal accruals (30 per cent) and debt (70 per cent).
DVC has planned to add three units of 500 MW at its existing thermal plants at Bokora and Mejia, both in Jharkhand. These units will be set up in the next three to four years.
Six greenfield projects aggregating 3,000 MW have been planned at Kodarma in Jharkhand (2x500 MW), Durgapur in West Bengal (2x500 MW) and Raghunathpur in West Bengal (2x500 MW). All these six projects will be ready by March 2012.
Ongoing projects: DVC expects its ongoing expansion at Mejia and Chandrapur, together worth 1,000 MW, to be completed within a year.
Joint ventures: DVC's joint venture with Tata Power to set up the 1,000 MW Maithon power project will be completed by March 2012. Besides, its joint venture with Steel Authority of India to set up a 500 MW plant at Bokaro will also be commissioned at the same time.