Damodar Valley Corporation (DVC) has plans to undertake a renovation and modernisation project for restoring the original capacity of its old units and extending their life by another 15 years.

 

DVC has proposed to invest Rs.1,363.6 crore in this project. The units, which would benefit from this project are three units of Bokaro A thermal power station (Jharkhand), all six units of Chandrapura thermal power station (Jharkhand) and one unit of the Durgapur thermal power station (West Bengal). The total capacity of these units is 1,092.5 MW, but these units have been derated to 980 MW.

 

However, the project would be undertaken only after confirming the techno-economic viability of these units, for which a residual life assessment study would be conducted.


After the renovation and modernisation project, the units concerned would be able to operate at 68 per cent plant load factor. Presently, these units operate at 37 per cent only.