Durgapur expressway to be re-tendered on annuity basisIllustrative image – not actual.

National Highways Authority of India (NHAI) has reportedly decided to re-tender the Durgapur expressway project in West Bengal, on annuity basis.

 

The project involves four-laning of 65 km of road between Dankuni and Palsit on NH-2 at a cost of around Rs.400 crore. This will be the first expressway to be developed on annuity basis.

 

Earlier, NHAI had invited requests for qualification (RFQ) for the project under the direct tolling method. Four bidders, viz. Gamuda, Road Builder (Malaysia), Larsen & Toubro and the IL&FS-CTNL combine, had responded to the RFQ.

 

With the decision to re-tender this project, eight projects will be tendered under the annuity method. These include the Tuni-Ankapalle, Tindivanam-Tambaram, Dharwad-Belgaum, Panagarh-Palsit, Rajahmundry-Dharmavaram, Dharmavaram-Tuni, Belgaum-Maharashtra border and the Durgapur expressway.

 