Dredging work starts at Paradip PortIllustrative image – not actual.

On 14 June 2008, Dredging Corporation of India commenced the work on Paradip Port Trust's channel deepening project, with launching of the dredger CSD Aquarius. Initially, cutter and suction dredger CSD Aquarius will do dredging, and subsequently higher capacity dredgers will be deployed to cater to the requirement.

The Rs.253.36 crore dredging contract has been awarded to the Dredging Corporation of India in January 2008. The scope of the work includes 15 million cubic metres of dredging - comprising 11.3 m in outer channel and another 3.7 cubic m inside the dock, including turning basin. On completion, the depth of the entrance channel will be increased from the present 12.8 m to 17.1 m and, as a result, the port will be able to handle Capesize vessels (125,000 dwt) capacity.

The work is expected to be over by June 2009.