Illustrative image – not actual.On 13 July 2001, Dabhol Power Company
stated that it would not recommence construction work of phase II (of 1,444 MW)
of the 2,184 MW power plant until and unless various issues related to the
project are settled.
Despite several meetings, no final agreement
between DPC and the Maharashtra government has been reached, towards restarting
the project.
Conciliatory negotiations between the government
of India and Enron Power Corporation – with a third arbitrator - are scheduled to begin during the last
week of July in New Delhi, prior to arbitration proceedings.
Meanwhile, financial institutions (FIs)
led by Industrial Development Bank of India (IDBI), have asked Enron to resume
work on phase II of the project. FIs including IDBI, IFCI, ICICI and State Bank
of India, have lent funds to the project.
On 10 July 2001, the Maharashtra government
ordered a judicial enquiry into the entire Enron episode starting from 1992. The
probe followed a meeting between the State Chief Minister, Mr Vilasrao Deshmukh
and the Chairman of Enron Corporation, Mr Kenneth Lay.