Illustrative image – not actual.The Railways has taken up work on Madurai-Vanchi Maniyachi-Tuticorin (Thoothukudi) doubling (160 km) with electrification. This includes earthwork, bridge works, ballast supply etc on the entire stretch.
The project was included in the Budget 2015-16 subject to requisite approvals. Sanction to the project and its detailed estimate amounting to Rs 1,182.31 crore was obtained in August 2017.
An expenditure of Rs 341.83 crore has been incurred up to March 2019. Moreover, an outlay of Rs 170 crore has been provided for the year 2019-20.
The Kadambur-Tattapparai (30 km) section is targeted to be commissioned during 2019-20. Madurai-Kalligudi (30.92 km) and Kalligudi-Satur (38.26 km) sections are planned for commissioning during 2020-21 and the remaining portion of the project is planned for commissioning by 2021-22.
The project was included in the Budget 2015-16 subject to requisite approvals. Sanction to the project and its detailed estimate amounting to Rs 1,182.31 crore was obtained in August 2017.
An expenditure of Rs 341.83 crore has been incurred up to March 2019. Moreover, an outlay of Rs 170 crore has been provided for the year 2019-20.
The Kadambur-Tattapparai (30 km) section is targeted to be commissioned during 2019-20. Madurai-Kalligudi (30.92 km) and Kalligudi-Satur (38.26 km) sections are planned for commissioning during 2020-21 and the remaining portion of the project is planned for commissioning by 2021-22.