Dombivli rail over bridge (ROB) has been dismantled in 15 days amid the lockdown. The Kalyan Dombivli Municipal Corporation (KDMC) and the Central Railway had started dismantling the bridge on 17 April 2020 and completed it by 30 April 2020.
The process would have taken around three months if the lockdown was not in place. The construction of the new bridge will begin soon.
The repair of the ROB will be undertaken by the Central Railway, while the desk-slab work of the bridge will be carried out by KDMC.
The repair work of the ROB and the underpass at Rajaji street is expected to be completed within six months.