Illustrative image – not actual.The Delhi Metro Rail Corporation (DMRC) is planning to commence trial runs on the first section of Phase-III of the Delhi metro rail project, from 30 December, 2013.
The trial runs will take place between Central Secretariat and Mandi House. The construction work for this three km underground stretch, which is part of the Central Secretariat -- Kashmere Gate Metro Line -- is almost complete and is expected to be opened for commuter operations by March 2014, after trials.
The DMRC will open the stretch before its scheduled date of October 2014. The Mandi House station will be the first interchange station of Delhi metro rail Phase-III.
The 69.57 km metro project, estimated to cost Rs 35,000 crore, will construct 38.46 km of underground section. It comprises a total of 28 underground stations.