Illustrative image – not actual.DMRC on 11 December 2012 submitted DPR of Mono Rail to Oommen Chandy, Chief Minister of Kerala at a function in Thiruvananthapuram.
As per the DPR prepared by Delhi Metro Rail Corporation (DMRC) and presented to the Chief Minister Oommen Chandy, the monorail with 19 stations in Phase I, will have provisions to extend to the south up to Neyyattinkara in Phase II and towards north as the Technocity expands. The 22.20-km monorail, an elevated rail-based MRTS, has been recommended in the Technocity – Pallippuram – Kazhakuttom – Uloor –Kesavadasapuram – Pattom – Palayam – Thampanoor –Killipalam - Karamana stretch of the capital.
The project stretch had been divided into three sections - Technocity to Karyavattom (7 km), Karyavattom to Kesavadasapuram (8 km), and Kesavadasapuram to Karamana (8 km) for speedy implementation of the project in five years.
The first section will be commissioned in 30 months after the turnkey contractor was finalised. The second stretch will be taken up only after the roads were widened. A car depot had been suggested at the Technocity end on 20 acre of government land. The stations had been mooted at Technocity, Pallippuram, Kaniyapuram, Kazhakuttom, Kazhakuttom Junction, Karyavattom, Gurumandiram, Pangappara, Sreekariyam, Pongumoodu, Ulloor, Kesavadasapuram, Pattom, Plamoodu, Palayam, Secretariat, Thampanoor, Killipalam, and Karamana.
Meanwhile, the design of civil structures and specifications for systems and train sets were exactly the same mooted for the Kozhikode Monorail. The two-track beams will be on circular pillars about 30 metres apart, along the median of the road. Two receiving sub-stations, one at the depot at Technocity and the other at Kesavadasapuram had been proposed.
Kerala Monorail Corporation (KMCL), the SPV, will implement the project. A total of 17.170 ha is needed for the project. Of this 13.750 ha is with government, 0.58 ha is with Railways, and 2.820 hectares with private parties. The project is estimated to come up with an investment of Rs 3,590 crore crore with the cost per route km being Rs.161.71 crore. It is expected to be completed by April 2019.