DMRC opens first segment of Chambakkara bridgeIllustrative image – not actual.

The Delhi Metro Rail Corporation (DMRC) has opened the first segment of Chambakkara bridge in Kerala for public on 9 May 2019.

The bridge has been opened 15 months after construction work started. With the opening of the new two-lane bridge, traffic on the existing old bridge has now been diverted to the new one.

The bridge is 7.5 mtr wide and 285 mtr long. The vehicles from Pettah side will use the old bridge to reach Vyttila side, while the vehicles from Vyttila side can use the new bridge to reach Pettah.

The total cost for construction of the two segments is Rs 69.13 crore. The new bridge will ease traffic congestion in the area.

The second segment of the bridge will be constructed after demolishing the existing old bridge.

The announcement of the project was made on 11 September 2017 and piling work began on 15 January 2018.

The work is an integrated one as both the bridges and the Metro run adjacent to each other. Work on the project is taken up in stages. In the next stage, peer cap, girder and duct slab will be placed as part of the Metro work.

Metro work is expected to be completed in three months. The construction on the second segment of the bridge will begin, following completion of the Metro work.

Foundation of the bridges has been completed. The construction work on the second segment of the bridge will be completed by March 2020, along with Metro work till Pettah.

 