DMRC completes work of third tunnel in phase II metro projectIllustrative image – not actual.

Delhi Metro Rail Corporation has completed the work of a third tunnel at Jorbagh, as part of the upcoming Central Secretariat-Gurgaon route under the second phase of Delhi metro.

The 951 mtrs down line tunnel passes beneath the Indian railway track and flyover at Safdarjung and the tunnelling was done 12 mtrs below the earth surface. For the purpose a tunnel boring machine, brought from Germany, was lowered on 19 February 2008.

A German laser system was used to guide the tunnel boring machine (TBM) along with the tunnelling process and about 38,000 cubic mtrs of earth was excavated for setting up the tunnel. Another parallel tunnel is being built on the up line which will be completed by end September end 2008.

For the phase two project, fourteen tunnel boring machines will be used simultaneously for the first time in India for building tunnels.

The second phase of the Delhi Metro Rail Corporation will comprise of 30-km of underground section of which 16-km are to be built using TBM.