Illustrative image – not actual.Delhi Metro Rail Corporation (DMRC) has completed the tunnelling work between INA and South Extension, under Phase-III of the Delhi metro rail project.
The Tunnel Boring Machine (TBM) made a breakthrough at the South Extension metro station site. This TBM, which was lowered at the INA shaft in October 2013, has completed a tunnelling drive of 925 mtr before being retrieved from the site. The other TBM, which is only 250 mtr behind in the adjacent tunnel, is also expected to be retrieved from the South Extension shaft in a fortnight.
The stretch is part of the over 58 km long Majlis Park (Mukundpur)-Shiv Vihar corridor of the Phase III network. This corridor includes 11 underground tunnelling stretches, including Lajpat Nagar, Sarojni Nagar, Bikaji Kama Place, Ashram and Hazrat Nizamuddin among others.
At present, tunnelling work is under execution between Sarojini Nagar and INA; between Shalimar Bagh - Netaji Subash Place; and between Azadpur - Shalimar Bagh underground stretches of Majlis Park - Shiv Vihar corridor of Phase III.
Phase-III of the Delhi metro rail project, estimated to cost Rs 35,000 crore, comprises six corridors in a total length of 69.57 km to metro network with 31.11 km of elevated section and 38.46 km of underground section.