The casting work of u-girders which will be installed on the elevated section of the Janakpuri West-RK Ashram corridor has been commenced under Phase IV, the Delhi Metro Rail Corporation (DMRC).
The casting work is being done at the designated casting yard for this section, located at Mundka. The u-girders, 28 mtr in length, will be subsequently installed on the corridor.
Every month 56 such u-girders will be produced at the casting yard. In total, about 2,200 different pre-cast components required for construction such as u-girders, pier-caps, cross-arms, pie-girders will be casted at the yard.
Despite issues such as unavailability of adequate labour force, DMRC is moving ahead with the construction work of all the three corridors approved so far as part of Delhi Metro's Phase-IV. Under the phase, 61.679 km of new Metro lines will be constructed across three different corridors comprising 45 Metro stations.
The 28.92 km long Janakpuri West-R. K Ashram Marg corridor is an extension of Magenta Line and will come up with 22 stations. Construction work on this particular section had started in December 2019.