Diversion channel project reaches pivotal stageIllustrative image – not actual.

The Water Resources Department (WRD) plans to start work this week in the crucial portion at Koyambedu junction, on Jawaharlal Nehru Salai.


This work will link flood water from Virugambakkam-Arumbakkam canal through a concrete channel to Cooum river.


The Rs 30 crore project is being executed by WRD.


Of the total distance of 2,400 mtr to be covered, only 110 mtr of the channel remains to be constructed. Presently, work is in progress at Kaliamman Koil Street near CMBT and will be completed in a few days.


About 100 blocks will be laid and WRD is expected to complete the entire project in a month.


 