Dilip Buildcon receives sanction letters to finance two road projectsIllustrative image – not actual.

Dilip Buildcon’s two wholly-owed subsidiaries DBL Rewa Sidhi Highways and DBL Chandikhole Bhadrak Highways have received the sanction letters to finance their hybrid annuity mode (HAM) projects.

DBL Rewa Sidhi Highways will undertake construction of road tunnel, viaduct and Churhat Bypass of Rewa Sidhi section of NH-75E from chainage 33.200 to chainage 55.400 (design length 15.350 km) as cement concrete pavement configuration in Madhya Pradesh on design, build, operate and transfer (DBOT) or HAM.

The company had placed the bid price of Rs 1,004 crore. The road project will be executed in a period of 48 months, while operation period will be for 15 years from COD.

DBL Chandikhole Bhadrak Highways will undertake rehabilitation and upgradation to six-laning of Chandikhole-Bhadrak Section of NH-5 (new NH-16) from 62.000 km to 136.500 km in Odisha to be executed as HAM project under NHDP Phase-V.

The company had placed the bid price of Rs 1,522 crore. The road project will be executed in a period of 30 months, while operation period will be for 15 years from COD.

Further, the SPVs have also submitted all the requisite financing documents to the National Highways Authority of India (NHAI) in accordance within the stipulated timelines given in the concession agreement related to the financial closure.

The company is in advance stage to get the sanction for the remaining HAM projects to achieve the financial closure as per the concession agreement.

 