Dilip Buildcon (DBL) has received a provisional completion certificate (PCC) for four-laning of the Dhrol-Bhadra Patiya section of NH-151A in Gujarat under public-private-partnership (PPP) mode on 04 November, 2023.
The authority has issued a PCC and has declared the project fit for entry into commercial operation as of 25 September, 2023.
The work entailed four-laning of the Dhrol-Bhadra Patiya section of NH-151A (between Ex. km 5+700 to km 13+600 of SH-25) and Bhadra Patiya-Pipaliya section of NH- (between ex. km 73+000 to km 44+800 and ex. km 38+350 to 24+000 of CSH-6) in the state.
The project, amounting to Rs 882.00 crore, had been carried out on a design, build, operate and transfer (DBOT) basis. On 28 October, 2021, DBL was appointed project work with a completion period of 730 days. The project was scheduled to be completed by 27 October, 2023.