Dilip Buildcon receives provisional certificate for Ambala-Kaithal sectionIllustrative image – not actual.

Dilip Buildcon (DBL) has received provisional certificate for four-laning of Ambala-Kaithal section of Haryana under NHDP Phase-III (Package-1) on EPC mode.

 

The scope of work involves four-laning of Ambala-Kaithal Section of NH-65 from 0.000 km to 50.860 km (Pehowa) with paved shoulder (length=50.860 km) which has been provisionally completed.

The provisional completion certificate has been issued by the authority on 11 December 2019. It has declared the project fit for entry into operation as on 13 December 2019. The cost of the road project is Rs 457.70 crore.

The appointed date for the project was 18 December 2015 and completion period was 913 days. The scheduled completion date was 17 June 2018.

← All latest storiesBack to top →